The new traffic signal at West Chestermere Drive and Station Way is operating, changing how motorists, pedestrians and cyclists move through the intersection after months of installation work.
The city is asking everyone using the crossing to follow the signals, pavement markings and signs, and to take extra care while drivers become familiar with the new arrangement.
The activation follows installation and testing of the signal equipment. The city says the improvements are intended to support safer crossings and smoother traffic movement at an intersection it identified as one of Chestermere’s busiest.
Council approved the project’s original $730,000 allocation from the Canada Community-Building Fund on June 24, 2025. That authorization covered the design and installation of traffic signals, a southbound left-turn lane and associated work.
On July 14, 2026, councillors approved a further $100,000, bringing the total authorized budget to $830,000. The approved amount represents the project budget. Final spending has yet to be confirmed.
Can-Traffic Services Ltd. carried out the signal installation on the city’s behalf. A construction notice issued Sept. 2 identified the following day as the anticipated start.
The work included rebuilding centre medians on West Chestermere Drive, installing signal poles with streetlight extensions, and adding cabinets for the traffic controller and electrical distribution.
Crews also used directional drilling and trenching to place underground conduit. The construction schedule separated the underground work and concrete bases from the later installation, wiring and testing of the poles and equipment.
At the outset, those later stages depended on delivery of the hardware, electrical inspection and a utility connection. Construction was planned for weekday daytime hours outside peak commuter periods, with the intersection remaining open and access maintained to businesses, parking lots and homes.
The intersection improvements had also appeared among recommendations in the Town Centre Traffic and Safety Study, which council accepted for information in December 2025. That study considered broader transportation needs, including pathways, roundabouts and a future transit hub.
For regular users of the Station Way crossing, the immediate change is visible on the road. The city’s message applies to people approaching on foot or by bicycle as well as those behind the wheel.
Residents can use the city’s road reports to check for construction affecting their route. Any remaining temporary signs, pavement markings and traffic-control directions should be followed as posted.
The city thanked residents for their patience during installation and testing and urged continued care as everyone adjusts.