Chestermere prepares for another crowded school year
Education

Chestermere prepares for another crowded school year

10 August 2026

Classes begin Sept. 2 as one new school rises in Dawson’s Landing and other projects remain in design or on the funding wish list By Stephen Jeffrey

Chestermere students will return to class Sept. 2 with the community’s public schools continuing to operate under enrolment pressure, even as several long-awaited construction projects move through different stages of Alberta’s school-funding system.

Rocky View Schools has repeatedly identified Chestermere as one of the division’s fastest-growing communities. The division expects to serve more than 29,600 students across its jurisdiction during the 2026–27 school year, with annual growth estimated at between 250 and 500 students.

The pressure is not new. RVS reported that Chestermere schools were operating at a combined utilization rate of 98 per cent during the 2023–24 school year. The division subsequently changed attendance boundaries and grade configurations to make better use of existing classrooms.

Those changes included expanding East Lake School from a Kindergarten-to-Grade 6 facility into a K–9 school. Students from Chelsea, Dawson’s Landing, Waterford and several other communities were also redirected to Rainbow Creek Elementary School for Kindergarten to Grade 6 and Chestermere Lake Middle School for Grades 7 to 9.

Additional modular classrooms have provided some short-term relief, but permanent schools take considerably longer to plan, fund and build.

The most advanced RVS project is a new Kindergarten-to-Grade 9 public school planned for Dawson’s Landing. The $53.2-million project has received construction funding and is intended to accommodate approximately 905 students.

RVS has not yet held a groundbreaking ceremony for the school, and a construction start date and opening date have not been announced.

A groundbreaking held in Dawson’s Landing on June 10, 2025, was for a separate K–9 Catholic school being developed by the Calgary Catholic School District. That project is not affiliated with Rocky View Schools.

The proposed RVS high school in Chelsea is at an earlier stage. The province initially provided planning funding in 2025 and advanced the project to design funding in July 2026. Design funding allows the project’s scope, layout, schedule and budget to be developed, but it is not the same as construction funding.

Rocky View Schools says the Chelsea facility would add 950 high-school spaces. Alberta’s Major Projects website lists a planned capacity of 1,055 students in Grades 10 to 12. The reason for the difference between those published figures has not been explained.

No construction start or opening date has been announced for the Chelsea project. RVS has said it will continue advocating for the school to advance to construction funding.

A third proposed school appears in the division’s longer-term capital priorities. RVS has ranked a new 890-student Kindergarten-to-Grade 6 school in Clearwater Park as its second-highest request for the 2027 provincial budget. The site is listed as ready, but the project has not received provincial construction approval.

The division cautions that a new school typically takes three to four years to complete after construction funding is approved. Having land identified or placing a project in a capital plan does not mean construction has been scheduled.

Families also face a more immediate deadline involving transportation. Registration for 2026–27 school bus service remains open, but the Aug. 1 deadline for guaranteed first-day service has passed. RVS has warned that registrations received after the deadline could face delays of up to three weeks. The annual transportation fee is $415 for students in Grades 1 to 12 and $207.50 for Kindergarten students who are subject to the fee.

The first day of classes for most RVS students is Wednesday, Sept. 2. Individual schools may issue additional instructions concerning staggered entry, registration and opening-day schedules.

For Chestermere families, the coming year will again be shaped by two different timelines: the daily work of fitting students into available classrooms and the much slower process of turning proposed schools into open buildings.

Construction funding for the RVS school planned in Dawson’s Landing represents progress, but the absence of an announced construction schedule means additional classroom space remains some time away. The Chelsea and Clearwater projects demonstrate how much work remains before Chestermere’s public-school capacity catches up with the community’s continued growth.